Initiation

Project setup and planning: the project becomes operationally real. Roles are clarified, the project team is appointed, resources are booked in, and the approach to Discovery (and possibly the whole project) is agreed. Ownership transfers to the Projects Coordinator and the Project Manager (from New Work or Account Management).


Roles


Typical activities


Deliverables

Deliverable Owner Shared With Format When
Project admin in place (Harvest, docs, repo) Projects Coordinator PM Harvest, Google Docs, Gitlab Before kick-off
PM onboarded Projects Coordinator PM Internal project initiation meeting template Day 1 of initiation
Risk register in place with known risks documented PM Project team + Sponsor Risk Register template By end of initiation
Decision register PM Project team Statement of Work template By end of initiation
Project resourced (roles confirmed) Projects Coordinator PM + Sponsor + Leads Internal project initiation meeting inc Support Before kick-off
Project Plan PM Project Team Project Management Sheet Internal kick-off
Statement of Work signed by client PM Project Team + client Statement of Work Before Discovery phase

Templates

Template Owner Audience
Statement of Work PM Both
Project Management Sheet PM Internal
Internal project initiation meeting Projects Coordinator Internal
Client K-O meeting PM Both
Board templates (Gitlab; other) Projects Coordinator Both

Tools and Platforms


Checkpoint

  1. Core project roles are assigned and accepted (Sponsor, Discovery, Design, Development, Backlog Steward, Support)Required output: Role confirmation documented in project workspace (project management sheet)

  2. Statement of Work is signed by clientRequired output: Scope and timeline are agreed and signed off

  3. Internal kick-off completedRequired output: Internal K-O meeting notes recorded; project documents updated

  4. Budget and timeline for Discovery are agreedRequired output: Documented in project management sheet

  5. Project infrastructure is in place (repo/backlog, tracking, comms, docs)Required output: Checklist signed off by PM

  6. Known risks are logged and visibleRequired output: Risk register created and accessible by client

  7. Client understands what Discovery will and will not coverRequired output: Discovery Plan document confirmed in writing or via kick-off notes

  8. Project plan signed offRequired output: Project plan includes phase with high-level estimates and timeline (currently in project management sheet)

If any of these is unclear, we resolve them before beginning Discovery.


Handover

From Projects Coordinator + Project Manager
To Discovery Lead + Project Manager
Mechanism Internal handover meeting. PM remains on the project; the Discovery Lead is formally introduced and confirmed.
Projects Coordinator Confirm resourcing is in place and the Discovery Lead is booked. Share the full project admin pack (risks, decisions, SoW, infrastructure).
PM Brief the Discovery Lead on the proposal, scope, risks, client context, and agreed Discovery approach. Ensure the project workspace is ready.
Discovery Lead Attend handover, confirm scope of their involvement, and take ownership of the Discovery plan.